City Manager Randall Eads provided an overview of the expansion of the scope of services for the landfill gas well installation contract awarded to APTIM Government Solutions, LLC on August 10, 2021. The expanded scope added up to five additional wells with two of the five wells being included in the current contract price.
Remarks begin at 3:00 and end at 4:27
City Manager Randall Eads explained that the two additional wells would be drilled near the “hot area” of the landfill to continue to extract gas. The contractor has drilled other wells but has encountered obstructions preventing them from drilling to the required depth.